History milestones
Choose years
2013
December

Huawei announced the start of its distribution hub at PCT S.A.

December
October
October

PCT is the leader of the first pilot set of the EU funded project INTE-TRANSIT “2C-MED12-05”.

June

Inauguration of Pier III of PCT S.A. under the presence of COSCO President Captain Wei Jiafu and Greek Prime Minister Mr. Antonis Samara.

June
June
June

50 meters of Pier III Quay Wall are completed.

May

Arrival of 6 new RMGs No. 17, 18,19,20,21& 22 at Pier III.

May
May
May

Arrival of 5 new SSPP Quay Cranes, QC31, QC32, QC33, QC34 and QC35 at Pier III.

April

2 RMG’s blocks and 28.500sq.m yard area of Pier III are completed.

April
April
April

400 meters of Pier III Quay Wall are completed

March

Hewlett Packard (HP) decides to use Piraeus as an additional gateway to EMEA region.

March
February
February

Inauguration of train service in PCT terminal.