History milestones
Choose years
2011
November

Fresh Water supply service to vessels.

November
November
November

225 meters in the middle of the East side of Quay Wall of Pier II are completed.

October

Visit of CPPCC Chairman Jia Qinglin and COSCO delegation.

October
October
October

Pier III constructions begun.

September

Arrival of 3 new SPP Quay Cranes, QC 18, QC 19 and QC 20.

September
July
July

225 meters of Quay Wall of the Northeastern part of Pier II are completed.

July

Constructions begun for warehouse inside PCT Terminal under the name “PCDC” – Piraeus Consolidation Distribution Centre.

July
June
June

1st year Anniversary of Independent Operations

May

Operation of Free Zone Type I in PCT

May
May
May

ISPS Code came into effect.

March

Provision of service for connecting and monitoring of reefer containers.

March
March
March

PCT undertakes the handling of Waste Management for vessels approaching Terminal.

March

350 meters of Quay Wall of the Southeastern part of Pier II are completed

March
February
February

350 meters of Quay Wall of the Northwestern part of Pier II are completed.

February

Arrival of the 8 new RMG’s at Pier II.

February